Standard Pitch Time (S.P.T) = Basic Pitch Time (B.P.T) + Allowances (%)
Target = (Total manpower per line *Working minutes)/ SMV * 100%
Theoretical Manpower = Benchmark target per hour/ Process capacity per hour
Labor Productivity = Total number of output per day per line/ Number of worker
worked
Machine Productivity = Total number of output per day per line/ Number of machine
used
Line Efficiency = (Total output per day per line* SMV ) / (Total manpower per line *
Total working minutes per day) *100%
Target = (Total manpower per line *Working minutes)/ SMV * 100%
Theoretical Manpower = Benchmark target per hour/ Process capacity per hour
Labor Productivity = Total number of output per day per line/ Number of worker
worked
Machine Productivity = Total number of output per day per line/ Number of machine
used
Line Efficiency = (Total output per day per line* SMV ) / (Total manpower per line *
Total working minutes per day) *100%