The critical path/TNA (Time & action) is a regular review systems to track progress of the project(s). In apparel industry the critical path/TNA (Time & action) is actually a production plan that contains a list of all activities required to be done in a time frame to ship the goods successfully within the estimated time of delivery (ETD). A smart merchandiser maintains critical path to identify the critical tasks, which if not attended to could impact delivery schedules for his styles.
Time & Action Calendar
Buyer
|
Li & Fung
|
Rib Fab Content
|
95%Ctn/5% Spandex
| |||||
Order #
|
JA-2376
|
Rib Fab GSM
|
190 GSM
| |||||
Style #
|
Boys-S6
|
Rib Consumption per Dz
|
200 gm
| |||||
Item
|
Crew Neck Tee
|
Total Rib Req
|
4500 Kg
| |||||
Body Fabric Content
|
100% Ctn
|
Yarn Count
|
24/S
| |||||
Body Fab Knitting Pattern
|
S/J
|
Spandex
|
40D
| |||||
Body Fab GSM
|
170 GSM
| |||||||
Gmts Ord Qty in pcs
|
240000
|
Machine Dia to be used
|
24 ,28, 30, 34
| |||||
Ord Confirmation Date
|
6/8/10
|
Yarn Count
|
28/S
| |||||
Del Date/ TOD
|
6-Oct
| |||||||
Body Fab Consumption per Dz
|
3.00 Kg
|
Finished fab requirement
|
60000 Kg
| |||||
SL
|
Color/Qty
|
S
|
M
|
L
|
XL
|
Total
| ||
1
|
Pink
|
10000
|
20000
|
20000
|
10000
|
60000
| ||
2
|
Olive
|
10000
|
20000
|
20000
|
10000
|
60000
| ||
3
|
Brown
|
10000
|
20000
|
20000
|
10000
|
60000
| ||
4
|
Aqua Blue
|
10000
|
20000
|
20000
|
10000
|
60000
| ||
5
|
Total
|
40000
|
80000
|
80000
|
40000
|
240000
| ||
SL#
|
Events
|
Action Date
|
Remarks
| |||||
1
|
Cargo must be at Ctg Port by
|
6-Oct
| ||||||
2
|
Cargo must leave factory not later than
|
5-Oct
|
Covered Van
| |||||
3
|
Final Insp to be offered not later than
|
3-Oct
| ||||||
4
|
Finshing must be completed not later than
|
2-Oct
| ||||||
5
|
All Washing (if any) must be completed not later than
|
1-Oct
| ||||||
6
|
All Sewing must be completed not later than
|
30-Sep
| ||||||
7
|
Bulk Production as per target must be achieved not later than
|
31-Aug
|
All Fab & Accy
| |||||
8
|
Input should be given in required lines to achieve day's Target prod not later than
|
30-Aug
| ||||||
9
|
Emb for day's prod qty must be in house not later than (if any emb)
|
29-Aug
| ||||||
10
|
Printing for day's tgt qty must be rcvd from printing not later than
|
28-Aug
| ||||||
11
|
Cutting should be done for required day's production as per ratio not later than
|
27-Aug
| ||||||
12
|
Size-set and PP must be approved not later than
|
24-Aug
| ||||||
13
|
All Lab-Test which may affect shipment to be completed not later than
|
30-Sep
| ||||||
14
|
Dyed fabric as per size/col ratio for day's production must be delivere to cutting not later than
|
26-Aug
| ||||||
15
|
Knitted Fabric for day's prod as per size color ratio must be delivered to cutting not later than
|
22-Aug
| ||||||
16
|
Knitting for day's garments production (as per ratio) must start not later than
|
19-Aug
| ||||||
17
|
Yarn must be at Factory for day's targetted qty not later than
|
17-Aug
| ||||||
18
|
BB L/C for yarn must be opened not later than
|
15-Aug
| ||||||
19
|
Master L/C must be received from Buyer not later than
|
11-Aug
| ||||||
20
|
Color Standard Must be received not later than
|
7-Aug
| ||||||
21
|
First Labdip to be submitted not later than
|
10-Aug
| ||||||
22
|
Product package must be received not later than
|
7-Aug
| ||||||
23
|
Proto Sample must be submitted not later than (with available Fabric)
|
8-Aug
| ||||||
24
|
All Accessories Development must be completed and approved not later than
|
16-Aug
| ||||||
25
|
All Accessories must be at Factory not later than
|
27-Aug
| ||||||
26
|
All washing approval (if any) must be obtained by
|
2-Sep
| ||||||
27
|
Sewing and Thread Must be at Factory by
|
28-Aug
|
total lead time 90 days,
ReplyDeletebut dyeing & delivery lead time only 20 day
knitting lead time 16 days
yarn in house complete only 5 days before from knitting complete date ?
order qty 60000 kg
how possible ?????????