Thursday, 12 February 2015

Production Calculation of Knitted Fabric


In every mill, there maintains a sequences in production processing in knitting. Production of a mill depends on a production manager. Among the various factors of calculation of knitted fabric are to be considered in the manufacture of knitted fabrics, it is very important for the knitter or production manager to calculate the productivity of a machine in order to be able to schedule production and specify the delivery dates to the customer. For calculation production manager need to know some formulas. Formula varies on different types of fabric. Different formulas for calculation of knitted fabric are given below  with example.
Fabric Type: Single Jersey Plain
Number of Feeder : 90 R.P.M. of Machine : 32
Machine Dia : 30 Machine Gauge : 24
Count of Yarn : 24/1 Ne Stitch Length : 2.74
Efficiency : 85 % No. of Machine : 20
Production Calculation of Knitted Fabric
= 10746.33 Kg
Fabric Type: 1 x 1 RIB
No of Feeder : 60 R.P.M. of Machine : 25
Machine Dia : 30 Machine Gauge : 20
Yarn Count : 34/1 Stitch length : 2.54
Efficiency : 80 % No. of Machine : 17
Production Calculation of Knitted Fabric
= 2441.65 Kg
Fabric Type: Plain Interlock
No of Feeder : 108 R.P.M. of Machine : 26
Machine Dia : 34 Machine Gauge : 24
Yarn Count : 34/1 Stitch Length : 1.54
Efficiency : 80 % No of Machine : 5

Production Calculation of Knitted Fabric
= 1108.50 Kg