Fashion Merchandising: Time and Action calendar
|
Introduction:
Time and Action (TNA)
calendar is one of the most important tools for managing a project. In
garment manufacturing each order is not less than a project to a merchant
because from order receiving to completion of an order it involves a number
of tasks of various timelines and utilization of various resources. Like
number of processes, lot of people are also involved to accomplish an order.
Similarly each order is unique in terms of process and time demand. So, a
detailed plan with well-defined responsibility is must in order to complete
each order to get completed on time.A time and action calendar defines the
ideal date/time period within which the major activities of an order should
occur against a scheduled delivery window.
TNA in
Garment Industry
Time and Action Calendar
or TNA, a popular tool used in apparel manufacturing industry is a technique
for tracking and following up of important milestones in preproduction
processes to ensure timely delivery within stipulated delivery date. Garment
pre-production and merchandising functions are characterized by people in an
organization doing multiple activities. While some of the activities are
dependent and follow each other, a few others are independent. Every garment
company takes enormous care during the planning of an order. Every little
detail is interwoven into the planning system. Making a TNA Calendar is not
just entering activity names and duration in tabular forms; it is also about
scientifically working-out the activity duration, logically determining the
preceding and succeeding activities.Time and action calendar consist of the
short term and long term plans so carefully laid out.
A time and action
calendar is a most effective communication tool that proves it to be useful
to this task. The chart consists of time frames listed for every action
planned (major ones) and these actions need to be earned out on time. The
purpose of TNA is to cross check at frequent intervals, say, once a week,
whether the planning is being executed satisfactorily. The more frequent the
checks, the easier it is to correct deviations. TNA is especially useful when
a buyer wants to know the status of execution of an order.
Structure
of TNA
Normally merchandisers prepare a plan of the order in a spreadsheet by listing down the key processes in first column and planned date of action for each process in the next column. This planning sheet is popularly known as time and action calendar (TNA). Once TNA calendar is made, then it can be easy for merchandiser list down their daily 'to do list' and taking it one by one. As per TNA schedule processes can be executed on timely basis to track whether an order is on track or it will get delayed.
In order to make TNA
below mentioned information must be available
- Process flow of an order
with the list of task which need to be performed
- Production capacity of
cutting, sewing, washing and finishing
- For sewing - batch wise
and product wise capacity (production per day per batch)
- Lead time of
activities, e.g. raw material lead time, sampling lead time, etc.
- Shipment date or
planned ex-factory date
Normally TNA does not
depend on fabric used in merchandise like woven or knits. TNA is largely
depends on the particular process flow of an order, machine requirement and
available production capacity. In TNA planned cutting date (PCD) and
ex-factory date these are the two most critical dates.
Sample TNA for formal shirt manufacturing order:
The TNA derived by
assuming the order of 10000 pieces of formal shirts, made out of 100% cotton,
plain woven solid dyed fabric, with embroidery logo on it. The order is for
SS 2013, delivery date 1stMarch 2013, shipment at New York-USA.
*All dates given are assuming Sunday as weekly holiday.
Importance of TNA
The importance of TNA can
be summarized.
Factors need to be
considered while preparing TNA:
Importance of key
activities in TNA
1. Sampling:
Sampling is the most
crucial task and hence need to plan in TNA very carefully, some sampling
stages are very important so any deviation or delay in that will affect the
whole TNA.
Proto
sample: The
submission of proto sample totally depends upon buyers enquiry date.Any delay
in proto submission or approval will affect order conformation date, which
will subsequently affect the submission of fabric development and fit sample,
as without proto approval it’s impossible to proceed further. In sample TNA
it is shown that the planned proto submission date is 09-06-2012 and planned
approval date is 27-06-2012, i.e. 15 working days are kept for proto sample
approval.
Fit
sample: After approval of proto sample manufacturer starts working on
fit sample, that needs to submit exactly at planned date. Any delay in fit
sample submission will cause the delay in P.O., size set sample submission.
Fit sample must submit within 45 days of proto approval as to get the sample
of bulk fabric it takes 20-25 working days to get in-house; hence after
approval of proto sample i.e. on 27-06-2012, the planned fit sample
submission date is 27-07-2012. Sometimes fabric suppliers are nominated by
buyer or buyer will supply the fabric in either case it may not take more
time. Hence, in time and action calendar approximate 1 month gap is shown
between proto sample approval and fit sample submission. Buyer must give the
comments on fit sample within 7 days. Any delay from buyer side will directly
affect the further process. To make fit sample process to complete
within time period, the planned approval date for fit is 22-08-2012 i.e. 21
days or 3 weeks is kept deliberately between first fit submission and
approval, in order to accommodate failures and re submissions of fit sample.
AD/Photo
shoot/Salesman sample: These samples are
generally submitted parallel with fit sample. The same period is allotted to
salesman sample i.e. 21 working days in TNA. These samples mainly used for
advertising or for visual merchandising or by sales man to collect the order
from retailers; hence from buyer’s perspective, timely submission of these
samples is very important. Order size mainly depends on this sample and any
delay or quality issue in sample can reduce the order size. Sometimes buyer
may ask more number of samples e.g. 100 pieces, in that case merchandiser
must keep in mind the capacity of sampling room, time required to complete
the demand of buyer, style complexity and buyers submission date while
making the TNA.
Size-set
sample: This stage of sampling is most important, without size set
approval bulk fabric for production should not be cut in order to accommodate
any changes by the buyer in the bulk production. So, any delay in size set
sample will directly affect PCD and subsequently affect the shipment date. Size
set sample need to submit with actual bulk fabric, hence for timely
submission of size set sample merchandiser should make sure that all bulk
fabric should be in-house well in advance of size set submission date. To
avoid the delay, as soon as bulk trims and fabrics are get in-house within 3
days size-set sample can be produced and submitted to buyer for approval. As
per TNA, in table no. 2, planned submission date of the size-set sample is on
08-10-2012 and expected approval is on 25-10-2012 i.e.15 working days
are kept for completion of size set sample approval process.
GPT
sample: Before submission of PP sample it is very necessary that Garment
Performance Test should be cleared from buyer. This sample sent to either
third party inspection or in-house testing lab. While preparing the TNA
merchandiser must keep in mind that test results should get approved from
buyer well in advance of PP meeting. For approval of GPT 20 days are kept in
TNA to deal with any delay in the process. Further, to avoid the delay in
submission of PP sample and PCD, GPT is happening along with Size-set sample
i.e. from 08-10-2012 to 30-10-2012.
Pilot-run: Before
going for actual production pilot run is carried out, in order to see the
complications in actual production and to give the sufficient time for
learning curve of operator on sewing floor. In TNA preparation one day is
kept for pilot run for smoother and uninterrupted production. As soon as
first few lots are cut, make sure that they will immediately send for embroidery.
Hence cut panels are available on time for pilot run. In sample TNA PCD is on
31-10-2012 while pilot run is planned on 03-11-2012, i.e. one day gap is kept
for embroidery of cut panels for pilot run. Pilot run can be conducted
before or after PP Meeting.
Pre-production
(PP) meeting and sample: Preproduction meeting is
very necessary part of any export order processing; hence merchandiser keeps
one day only conducting PP meeting, in order to discuss the expected
difficulties during production. Any delay in this meeting or if more
obstacles are there to solve in production will directly affect the PCD and
ultimately results in shipment delay.
PP sample need to submit
within 10 days after approval of size-set and GPT samples. As without
approval of PP sample production should not start.To maintain the PCD
merchandiser should be very careful while preparation of TNA for PP sample.
PP sample is normally pooled out from pilot-run, hence submission date for PP
sample is 03-11-2012 and approval date is 12-11-2012 i.e. 6 working days gap
is kept for PP sample.
Top of
production sample: As soon as production starts and first
few pieces are come out of line TOP sample need to submit to buyer. It’s very
crucial stage where merchandiser must keep in mind that by any reason TOP
sample get rejected then production end date is going to be delayed. This can
straight way affects the shipment date. In sample TNA, it is shown that
sample is submitted on 17-11-2012 and planned approval date is 21-11-2-12.
2. Fabric and trim
sourcing:
Fabric and trim sourcing
is very time consuming process which includes desk loom and lab-dip
approvals, trim and art work approval, FPT approval. The fabric sourcing
itself will take lead time of 30-60 days depending upon type of fabric. For yarn
dyed fabric it takes approx. 45 day, for piece dyed fabric it take approx. 30
days and for fibre dyed fabric it takes approx. 55-60 days. In sample TNA, it
is assumed that fabric used is solid dyed hence 30 days lead time is
considered while preparing the TNA, trims also takes the approximate 30-45
days depending upon from where trims are getting sourced. Hence while
designing the TNA for sourcing the following activities need to keep in mind.
Fabric
approvals: With approval of proto sample, merchandiser needs to submit
lab-dip for colour conformation. Lab-dip approval itself is a long process,
as development of shade and submission itself will take 10-15 working days
for one attempt, hence for after 15 days of proto approval Lab dip is
submitted. Hence while preparing the TNA merchandiser must keep in mind that,
complexity of shade, buyer’s specification etc. any delay in lab-dip
submission will end up with fabric production delay, which will results in
delay in; Size-set sample submission. Hence to avoid the delay in TNA 30
working days buffer is kept from submission date i.e. 14-07-2012 to planned
approval date i.e.20-08-2012.
Trims
and art work: Trims and their art work are other important factors of sourcing
department after fabric. Timely approval of trims is very necessary. Trim
production and shipment is also time consuming process, especially if it is
imported, hence while preparing the TNA 25 working days buffer is kept
between submission date i.e.14-07-2012and approval date13-08-2012.
Fabric Performance
Test (FPT): Before fit sample submission date FPT report must be approved by
buyer, as fit sample submitted in similar fabric. As without approval of FPT
fabric supplier can’t ship the fabric to garment manufacturer. Any delay in
FPT submission in will cause in fit sample submission and may show impact on
fabric in-house date which will subsequently affect the size-set submission
date.
3. Production
The most crucial part of
any TNA is actual production. While preparing the TNA for production following
activities need to consider.
Planned
Cut Date: The most important date for both sourcing and merchandising
department. Most of the time, TNA is prepared by keeping PCD in mind. To
achieve the PCD on time sourcing department plays important role, as lead
time of trims and fabric production and availability for garment production
is controlled by this department. While preparing the TNA expected lead time
and sufficient buffer should keep for sourcing.
As there is embroidery
included on cut panels, hence after cutting the cut panels need to send for
embroidery. Considering that embroidery is in-house then 6 working days after
PCD to complete the embroidery need to be consider in TNA. If embroidery is
outsourced then accordingly more number of days can be included in TNA.
In some merchandise, washing, printing is required hence merchandiser need to take care of the lead time requirement for the same including necessary buffer.
Productions
start and end date: These two dates are purely depends upon shipment
date and production capacity. As soon as PCD is achieved the production
should start immediately after pilot run and approval of PP Sample. Any
deviation in this date will subsequently affect the TOP sample submission
date and shipment date. Number of days required for production is decided by
capacity allocated to that particular merchandise or number of days of
available for actual shipment. For mentioned sample TNA, following
assumptions were made while calculating the number of days required completing
the production.
Assumptions: No. of pieces= 10000 SAM of garment= 28.5 min No. of M/c= 50 Efficiency = 45% The calculation for production days can be shown as:
So, if 25 working days
needs for production, then production will start on 15-11-2012 and it will
end on 15-12-2012, if only one sewing line of 50 machines is allocated for
10000 pieces.
Finishing
and packing: As finishing and packing is equally important, hence as soon as
first lot comes out of production, finishing and packing get started. This
can be started parallel along with production. In sample TNA, 17-11-2012 is a
starting date of finishing and packing, while 18-12-2012 is end date. 3 days
buffer is kept deliberately between production date and finishing packing
completion date to avoid any consequences.
Apart from these main
activities, following constraints merchandiser should keep in mind while
preparing the TNA for production.
Any delay in production
will directly leads to shipment delay hence for actual production proper
buffer should be allocated in TNA.
Critical Path method for
TNA preparation:
Fashion merchandising is
a much complicated network of linier and non-linier activities to perform.
Activities performed are interdependent and need of synchronization between
succeeding and preceding activities to make a non-linear process network. The
longest chain of activities considering task dependencies is called critical
path. It is a common practice industry to list activities from order receipt
to delivery in linear sequence and assigning time duration to each activity
by backward planning, which is wrong as the activities are never linear since
there are lot of parallel activities. Therefore, the sequence of activities
should be drawn either as PERT network or Gantt chart format.
Even though most of the
users are aware of the term 'critical path method' (CPM), CPM may be
elaborated as ‘critical’ means 'possibility of non-conformance is higher' as
per previous experience; some even link 'critical' with cost involving that
activity. Everybody select 'critical' activities hypothetically based
on intuition or previous experience or buyer's milestones and no one actually
makes PERT network of activities and then arrive at CPM.
It was found that in majority of the cases the buyer specifies target dates of key activities and based on those target dates the manufacturing organization creates their own TNA adding buffer days (to ensure that buyer target dates are not missed). It was also a common practice to have two TNA: one with few main important activities (also called milestone activities) that are suggested by the buyer, and another one with more number of in-between micro activities (in-house activities) to exercise control over macro activities PERT network or Gantt chart should be mandatorily prepared to decide upon which all activities should be there in TNA calendar. Merchandiser must prepare either and the resultant critical path should be the activity chain for TNA calendar, all activities falling in critical path are critical activities. Critical activities should always be on focus, a single minute delay in any of the critical activities may lead to final shipment delay.
Conclusion:
Garments manufacturing is
not a business of 'One Man Show' rather it is a Team-Work where lot of
people, organizations, suppliers, buyer, sub-contractors and manufacturers
are involved. Moreover, all tasks have to be accomplished with in a given
time frame to ship out the garments on time. Buyer will not accept any delay
in the garments delivery and if the garments cannot be shipped out on time
then there will be good possibility thatbuyer may cancel the order or may ask
for air shipment or Buyer may ask for discount. To avoid all such adverse
situation merchandiser need to do proper planning to execute any order.
TNA is most important
activity for timely shipment. If any merchandiser is able to follow the TNA
properly then it will be not a big challenge to ship the garments on
schedule.TNA for any production unit is summery of sampling, sourcing and
production activities and their sub activities. Merchandiser generally
makes the TNA on the basis of lead time mentioned by buyer, shipment date
negotiation, order quantity, production capacity. The milestones and
key/critical activities dates are mentioned by buyer while other in-house
activities need to manage by merchandiser by keeping many things in mind.
With the help of TNA merchandisers can ensures satisfaction of each and every
step with constant follow ups and in shortest cycle time possible. Rapidly
changing trends of the fashion industry is making merchandising activities
more complicated and so TNA. Merchandiser has to prepare good and flexible
TNA by keeping all facts and facets in mind. If used effectively, a good TNA
can help factory to meet production and shipment deadlines, increase inventory
turns, improve customer service, and enhance profits.
|
No comments:
Post a Comment